Missouri Construction Lien Resources

Original contractors: Notice to Owner before the first payment. Subs and suppliers: 10-day notice before filing. File the lien within 6 months. Sue within 6 months of filing. Everything a contractor, subcontractor or supplier needs to protect lien rights in Missouri.

ACCURATE. ON TIME. ON YOUR SIDE.Mo. Rev. Stat. 429.005 et seq.Last reviewed October 6, 2026

Start a Missouri jobCalculate my deadlines

10days

Subs and suppliers: notice to owner before filing the lien

6months

File the lien after the debt accrues

6months

Sue to enforce after the lien is filed

90days

Public jobs: remote supplier notice to the contractor

Tool

Missouri deadline calculator

Enter your dates and see every deadline in order. Red rows are the ones that can cost you the lien.

Process

How a Missouri lien comes together

  1. Before any payment

    Original contractor gives Notice to Owner

    The original contractor gives the statutory notice in ten-point bold type to the person it contracts with, or to the owner if there is no contract. It goes out at contract signing, at delivery, at the start of work, or with the first invoice.

    Mo. Rev. Stat. 429.012.1

  2. Within 15 business days after rental use starts

    Rental equipment notice (equipment rental claims only)

    A party claiming a lien for rental machinery or equipment must notify the owner in writing within 15 business days after use starts. Rental liens apply only on commercial property and to claims over $5,000.

    Mo. Rev. Stat. 429.010

  3. At least 10 days before filing

    Subs and suppliers serve notice to the owner

    Everyone except the original contractor gives the owner or agent 10 days’ notice before filing. The notice states the amount and who owes it.

    Mo. Rev. Stat. 429.100

  4. Within 6 months after the debt accrues

    File the lien with the circuit clerk

    File a verified account and a property description with the circuit court clerk in the county where the property sits. Rental equipment claims must be filed within 60 days after the equipment was last removed.

    Mo. Rev. Stat. 429.080

  5. Within 6 months after filing

    Start the enforcement suit

    File suit to enforce the lien within six months after filing it. If no suit is filed in time, the lien stops existing.

    Mo. Rev. Stat. 429.170

Plain English

The Missouri rules, abstracted

A working summary of the Missouri Mechanic’s Lien Law for notice, recording and enforcement.

Who has lien rights

Anyone who performs work, rents or uses rental machinery or equipment, or furnishes materials, fixtures or machinery for an improvement on land has lien rights. The work must be under a contract with the owner or the owner’s agent, trustee, contractor or subcontractor. This includes landscapers and outdoor irrigation installers. Registered architects, engineers, landscape architects and land surveyors have lien rights under a separate section, 429.015.

Original contractor’s Notice to Owner

Every original contractor must give a written notice in ten-point bold type before receiving any payment. It goes to the person the contractor contracts with, or to the owner if there is no contract. It can go out at contract signing, at delivery, at the start of work, or with the first invoice. The notice is a condition precedent to the original contractor’s lien. It does not apply to new residences where the buyer gets lien protection through a Missouri-registered title insurance company.

Subcontractor and supplier notice before filing

Missouri has no general preliminary notice at the start of a job. Instead, every claimant other than the original contractor must give the owner or agent 10 days’ notice before filing the lien. The notice states the amount claimed and who owes it. Any officer authorized to serve civil process may serve it, and the officer’s return is the proof. Any person who would be a competent witness may also serve it, and that person signs an affidavit of service.

Filing the lien

File the lien with the clerk of the circuit court in the county where the property is located. The deadline is six months after the debt accrued. The filing includes a just and true account after all credits, a property description, and the owner’s or contractor’s name if known. It must be verified by oath. Rental equipment claims must be filed within 60 days after the equipment was last removed from the property.

Enforcing the lien

The claimant must start a lawsuit within six months after filing the lien. If no suit is filed in that window, the lien no longer exists.

Owner-occupied residential repairs and remodels

This rule covers repairs, remodels and additions to owner-occupied homes of four units or less. On these jobs, anyone other than the original contractor has no lien unless the owner signed a separate Consent of Owner in the statutory form and a copy is attached to the lien. Without the consent, full payment to the contractor is a complete defense. The rule does not apply to building the original residential unit.

Residential real property sales: notice of rights

Section 429.016 covers residential real property as that section defines it. It does not cover owner-occupied repairs and remodels, which 429.013 governs. An owner may record a notice of intended sale at least 45 calendar days before the earliest intended closing date. Claimants must then record a notice of rights with the county recorder of deeds at least five calendar days before the stated closing date. A claimant who fails to record forfeits its lien rights against that property.

Missouri quirks

An advance lien waiver given in exchange for being awarded a contract or subcontract is against public policy and unenforceable. A contract may still require lien waivers as a condition of payment. On public projects, a payment bond bars mechanic’s liens by subs and suppliers. A lien filed in violation is void. Since August 28, 2025 (HB 199), a local public entity may record its consent to mechanic’s liens on a project intended to be leased mainly to a private entity for nongovernmental use. If it does, no bond is required.

Where Missouri liens go wrong

  • Original contractors skipping the bold-type Notice to Owner before taking the first payment.
  • Subs and suppliers filing the lien without serving the owner at least 10 days ahead.
  • Letting six months pass after filing without starting the enforcement suit.
  • Subs on owner-occupied home remodels filing without a signed Consent of Owner attached.
Checklist

What do I need to send?

  • Ask the original contractor for any signed Consent of Owner on owner-occupied remodels.
  • Serve the owner or agent at least 10 days before filing, stating the amount and who owes it.
  • File the verified lien with the circuit clerk within six months after the debt accrues.
  • Start the enforcement suit within six months after filing.
  • On bonded public jobs, remote suppliers send written nonpayment notice to the contractor within 90 days after last supplying materials.
  • Give the statutory Notice to Owner in ten-point bold type before receiving any payment.
  • Keep copies of the notice and any signed owner consent.
  • File the verified lien with the circuit clerk within six months after the debt accrues.
  • Start the enforcement suit within six months after filing.
  • On public works estimated to cost over $50,000, furnish the required payment bond.
  • Expect the original contractor’s Notice to Owner before the first payment.
  • Contracts may require lien waivers as a condition of payment.
  • On owner-occupied home remodels, signing a Consent of Owner opens the door to sub and supplier liens.
  • Before selling residential real property covered by 429.016, an owner may record a notice of intended sale at least 45 days before closing.
  • Watch for 10-day notices from subs and suppliers before they file.
Public jobs

Public projects: payment bonds

You can’t lien public property. On state and local jobs, your security is the contractor’s payment bond under the Missouri public works bond statute, Mo. Rev. Stat. 107.170 and 522.300.

  • Public entities must require a payment bond on public works estimated to cost over $50,000. The bond covers materials, insurance premiums and labor. Claimants sue on the bond in the name of the public entity.
  • A remote supplier is a supplier with a contract with a second-tier or lower subcontractor, or with another supplier of any tier. A remote supplier must give the contractor written nonpayment notice within 90 days after last supplying materials.
  • A bond under 107.170 bars mechanic’s liens by subs and suppliers. A lien filed in violation is void and unenforceable.
  • Since August 28, 2025 (HB 199), no bond is required if the public entity executes and records a consent to mechanic’s liens under 513.455.

Mo. Rev. Stat. 107.170; 522.300; 513.455

Payment

Lien waivers

The Chapter 429 sections reviewed set no statutory lien waiver form. An agreement to waive lien rights in advance, in exchange for being awarded a contract or subcontract, is against public policy and unenforceable. A contract may still require lien waivers as a condition of payment. Under 429.016, a claimant who recorded a notice of rights and was paid in full must give an unconditional final lien waiver no later than five calendar days after a written request.

Mo. Rev. Stat. 429.005; 429.016

Federal projects

The Miller Act governs federal jobs in every state. Second-tier claimants give written notice to the prime contractor within 90 days after last furnishing; suit within 1 year after last furnishing.

40 U.S.C. 3133

Primary source

Read the Missouri law

We link to the official statute instead of hosting a copy, so you always read the current version. Our summaries were last checked against these sources on October 6, 2026.

Pricing

Missouri services

Flat pricing per document. Premium members pay less on every filing.

Basic: free with signup. Premium: $299 per year.

Basic Membership

Create your free LienNow account to access all our services at standard pricing. No cost, no commitment.  Sign up in minutes and start filing right away at our standard pricing. It’s a good fit for contractors and suppliers who file occasionally.

Premium Membership

Premium includes everything in Basic, plus discounted pricing across our service offerings. If you file notices or liens regularly, the savings can quickly cover the annual fee.

Service Premium Basic
Rental equipment notice to owner Starting at $55 Starting at $90
Notice to owner (original contractor) Starting at $55 Starting at $90
10-day notice before filing Starting at $75 Starting at $110
Mechanic’s lien statement: prepare, record and serve Starting at $250 Starting at $425
Lien release / discharge Starting at $110 Starting at $165
Public job bond notice or claim Starting at $210 Starting at $375
Miller Act bond notice or claim (federal jobs) Starting at $195 Starting at $350
Title search and legal description Starting at $300 Starting at $350
Rush service (within 7 business days) Starting at $75 Starting at $150
Same-day service (24-hour turnaround) Starting at $125 Starting at $200
Electronic recording (e-file) Starting at $45 Starting at $75

Prices are LienNow service fees per document. County recording fees, state registry or portal fees, certified mail, postage and notary fees are billed at cost. Court actions to enforce a lien are handled by an attorney and are not included.

FAQ

Missouri lien questions

Does Missouri require a preliminary notice at the start of a job?

Not for most subs and suppliers. Original contractors must give a Notice to Owner before receiving any payment. Subs and suppliers must give the owner 10 days’ notice before filing a lien. Rental equipment lien claimants on commercial jobs must notify the owner within 15 business days after use starts.

How long do I have to file a Missouri mechanic's lien?

Six months after the debt accrued. File it with the circuit court clerk in the county where the property sits. Rental equipment claims must be filed within 60 days after the equipment was last removed.

How long does a Missouri lien last?

Six months after filing, unless a suit to enforce it is started within that time.

Can a subcontractor lien an owner-occupied home remodel?

Only if the owner signed a separate Consent of Owner in the statutory form and a copy is attached to the lien. This applies to repairs, remodels and additions on owner-occupied homes of four units or less.