20-day Notice of Furnishing. 90 days to record. One year to enforce. Everything a contractor, subcontractor or supplier needs to protect lien rights in Michigan.

ACCURATE. ON TIME. ON YOUR SIDE.MCL 570.1101 et seq.Last reviewed September 29, 2026

Start a Michigan jobCalculate my deadlines

20days

Notice of Furnishing after first furnishing

90days

Record the Claim of Lien after last furnishing

15days

Serve the recorded lien on the designee

1year

Foreclose after the lien is recorded

Tool

Michigan deadline calculator

Enter your dates and see every deadline in order. Red rows are the ones that can cost you the lien.

Process

How a Michigan lien comes together

  1. Before or at start

    Request the Notice of Commencement

    Send a written request by certified mail. The owner, lessee or designee must provide a copy within 10 days after the request is mailed.

    MCL 570.1108

  2. Day 20 from first furnishing

    Serve the Notice of Furnishing

    Subcontractors and suppliers serve the designee and the general contractor named in the NOC, personally or by certified mail.

    MCL 570.1109

  3. During the job

    Track payments, sworn statements and waivers

    Payments the owner makes against a sworn statement or waiver before your notice arrives can reduce a late notice’s lien.

    MCL 570.1109(6), 570.1110

  4. Day 90 from last furnishing

    Record the Claim of Lien

    Record with the Register of Deeds in the county where the property sits.

    MCL 570.1111(1)

  5. 15 days after recording

    Serve the recorded lien

    Serve the designee (or owner/lessee if none) personally or by certified mail, return receipt requested. Certified mail service is complete on mailing.

    MCL 570.1111

  6. 1 year after recording

    File suit to foreclose

    Record a lis pendens when the action is filed.

    MCL 570.1117

Plain English

The Michigan rules, abstracted

A working summary of the Construction Lien Act for notice, recording and enforcement.

Who has lien rights

Contractors, subcontractors, suppliers and laborers who furnish labor or material for an improvement to real property. A contractor must provide a sworn statement before it can enforce its lien or collect payment.

Notice of Commencement

The owner or lessee records the NOC with the Register of Deeds and posts it on site. It names the designee who receives notices. Any claimant can demand a copy by certified mail and must receive it within 10 days. The NOC rules in 570.1108 do not apply to residential structures; 570.1108a sets a separate residential process.

Notice of Furnishing

Subcontractors and suppliers serve it within 20 days after first furnishing, on the designee and the general contractor named in the NOC, personally or by certified mail. Late notice does not kill the lien, but the lien is reduced by payments made against sworn statements or waivers before the notice was served. Laborers have separate deadlines tied to unpaid wages and benefits, and a laborer’s failure to give notice defeats the laborer’s lien.

Claim of Lien

Record within 90 days after your last furnishing, in each county where the property is located. Serve a copy on the designee (or owner/lessee) within 15 days after recording, personally or by certified mail, return receipt requested.

Enforcement

Foreclosure must be filed within 1 year after the claim of lien is recorded, with a notice of lis pendens recorded at filing.

Residential

On a residential structure, the lien does not attach to the extent the owner or lessee files an affidavit showing they paid the contractor (MCL 570.1118a). That makes early notice and payment tracking critical on homes.

Where Michigan liens go wrong

  • Counting 90 days from the invoice date instead of the last day you actually furnished labor or material.
  • Serving the notice on the owner when the NOC names a different designee.
  • Recording the lien but missing the 15-day service after recording.
  • Letting a late Notice of Furnishing ride while the owner keeps paying against sworn statements.
Checklist

What do I need to send?

  • Request for Notice of Commencement (certified mail)
  • Notice of Furnishing within 20 days
  • Claim of Lien within 90 days of last furnishing
  • Service of recorded lien within 15 days
  • Sworn statement before enforcement
  • Sworn statement with each payment request
  • Claim of Lien within 90 days of last furnishing
  • Service of recorded lien within 15 days
  • Record and post the Notice of Commencement
  • Respond to NOC requests within 10 days
  • Collect sworn statements and statutory waivers before paying
Public jobs

Public projects: payment bonds

You can’t lien public property. On state and local jobs, your security is the contractor’s payment bond under the Public Works Bond Act, MCL 129.201 et seq..

  • Claimants without a direct contract with the principal contractor serve a written notice on the principal contractor within 30 days after first furnishing.
  • All claimants give written notice to the principal contractor and the governmental unit within 90 days after last furnishing.
  • Notices go by certified mail, postage prepaid.
  • Suit must be filed within 1 year from the date final payment was made to the principal contractor.

MCL 129.207, 129.209

Payment

Lien waivers

Michigan prescribes four statutory waiver forms: partial conditional, partial unconditional, full conditional and full unconditional. Waivers must be in substantially the statutory format.

MCL 570.1115

Federal projects

The Miller Act governs federal jobs in every state. Second-tier claimants give written notice to the prime contractor within 90 days after last furnishing; suit within 1 year after last furnishing.

40 U.S.C. 3133

Primary source

Read the Michigan law

We link to the official statute instead of hosting a copy, so you always read the current version. Our summaries were last checked against these sources on September 29, 2026.

Pricing

Michigan services

Flat pricing per document. Premium members pay less on every filing.

Basic: free with signup. Premium: $299 per year.

Basic Membership

Create your free LienNow account to access all our services at standard pricing. No cost, no commitment.  Sign up in minutes and start filing right away at our standard pricing. It’s a good fit for contractors and suppliers who file occasionally.

Premium Membership

Premium includes everything in Basic, plus discounted pricing across our service offerings. If you file notices or liens regularly, the savings can quickly cover the annual fee.

Service Premium Basic
Request for Notice of Commencement Starting at $35 Starting at $60
Find missing or correct wrong address Starting at $50 Starting at $75
Notice of Furnishing Starting at $50 Starting at $90
Property research / investigation Starting at $80 Starting at $120
Claim of Lien: prepare and record Starting at $195 Starting at $350
Release and discharge of Claim of Lien (recorded) Starting at $95 Starting at $150
Unrecorded release and discharge Starting at $60 Starting at $150
Bond notice or lien on bond (state public jobs) Starting at $195 Starting at $350
Each additional surety notification Starting at $55 Starting at $75
Miller Act bond notice or claim (federal jobs) Starting at $195 Starting at $350
Title search and legal description: Oakland, Wayne, Macomb, Washtenaw Starting at $200 Starting at $250
Title search and legal description: all other counties Starting at $300 Starting at $350
Title search with foreclosure search: Oakland, Wayne, Macomb, Washtenaw Starting at $500 Starting at $600
Title search with foreclosure search: all other counties Starting at $600 Starting at $700
Notice of Commencement kit (non-designee) Starting at $180 Starting at $225
Notice of Commencement, designee full service: job under $450,000 Starting at $300 Starting at $425
Notice of Commencement, designee full service: job $450,000 or more Starting at $500 Starting at $625
Rush service (within 7 business days) Starting at $75 Starting at $150
Same-day service (24-hour turnaround) Starting at $125 Starting at $200
Electronic recording (e-file) Starting at $45 Starting at $75

Prices are LienNow service fees per document. County recording fees, state registry or portal fees, certified mail, postage and notary fees are billed at cost. Court actions to enforce a lien are handled by an attorney and are not included.

FAQ

Michigan lien questions

Is the Notice of Furnishing required in Michigan?

It is required for subcontractors and suppliers. Serving it late does not defeat the lien, but the lien is reduced by payments made against sworn statements or waivers before your notice was served.

When is the 90-day lien deadline measured from?

From your last furnishing of labor or material for the improvement, not the invoice date or the project completion date.

Does certified mail have to be delivered to count?

For the recorded lien, the statute says service by certified mail is complete upon mailing.

How long does a Michigan construction lien last?

A foreclosure action must be filed within 1 year after the claim of lien is recorded.