Notice to Contractor within 30 days (when an NOC is filed), file the lien within 90 days of completion, sue within 365 days of filing. Everything a contractor, subcontractor or supplier needs to protect lien rights in Georgia.

ACCURATE. ON TIME. ON YOUR SIDE.O.C.G.A. 44-14-360 et seq.Last reviewed October 6, 2026

Start a Georgia jobCalculate my deadlines

30days

Notice to Contractor (if a Notice of Commencement is filed)

90days

File the claim of lien after completing work

2business days

Send a copy of the lien to the owner

365days

Start the lien action after filing

Tool

Georgia deadline calculator

Enter your dates and see every deadline in order. Red rows are the ones that can cost you the lien.

Process

How a Georgia lien comes together

  1. Within 15 days after the contractor starts work

    Notice of Commencement

    The owner, the owner’s agent, or the contractor files a Notice of Commencement with the superior court clerk. A copy is posted on the job site.

    O.C.G.A. 44-14-361.5(b)

  2. Within 30 days of first furnishing (optional)

    Preliminary Notice of Lien Rights

    A lien claimant may choose to file a Preliminary Notice of Lien Rights with the superior court clerk. Claimants other than the contractor must mail a copy to the contractor or owner within 7 days of filing.

    O.C.G.A. 44-14-361.3(a), (b)

  3. Later of 30 days after the NOC is filed or 30 days after first delivery

    Notice to Contractor

    If a Notice of Commencement is filed, a claimant with no privity of contract with the contractor sends a Notice to Contractor to the owner (or agent) and the contractor. Use registered or certified mail or statutory overnight delivery.

    O.C.G.A. 44-14-361.5(a), (c)

  4. Within 90 days after completing work

    File the claim of lien

    File the claim of lien with the clerk of the superior court in the county where the property is located. It must include the expiration statement and the notice of the owner’s right to contest.

    O.C.G.A. 44-14-361.1(a)(2); 44-14-367

  5. Within 2 business days after filing

    Send copies of the lien

    Send a true copy to the owner by registered or certified mail or statutory overnight delivery. If an NOC is filed, also send a copy to the contractor at the NOC address.

    O.C.G.A. 44-14-361.1(a)(2)

  6. Within 365 days after filing

    Start the lien action

    File suit within 365 days of filing the lien. Within 30 days after filing suit, file a notice of the action with the superior court clerk. The lien expires 395 days after filing if no notice of the action is filed.

    O.C.G.A. 44-14-361.1(a)(3); 44-14-367

Plain English

The Georgia rules, abstracted

A working summary of the Georgia Mechanics’ and Materialmen’s Lien Law for notice, recording and enforcement.

Who has lien rights

Georgia gives lien rights to contractors, subcontractors, laborers, and material suppliers. Architects, registered foresters, land surveyors, professional engineers, and registered interior designers can also claim liens.

Pre-lien notices

Georgia has two. The Notice to Contractor applies only when a Notice of Commencement is filed. It applies to claimants without privity of contract with the prime contractor. It is due within 30 days after the NOC is filed or 30 days after first delivery, whichever is later. It goes to the owner (or agent) and the contractor by registered or certified mail or statutory overnight delivery. The statute makes it a condition to "make good" the lien. The Preliminary Notice of Lien Rights is optional. It is filed with the superior court clerk within 30 days after first furnishing. Claimants other than the contractor mail a copy to the contractor or owner within 7 days.

Notice of Commencement

The owner, the owner’s agent, or the contractor files a Notice of Commencement no later than 15 days after the contractor physically starts work. It is filed with the superior court clerk and posted on the job site. If no NOC is filed, the Notice to Contractor rules do not apply.

The claim of lien

File the claim of lien within 90 days after completing the work or furnishing the materials. File it with the clerk of the superior court in the county where the property is located. The lien must include a statement that it expires and is void 395 days after filing if no notice of the lien action is filed. That statement must be in at least 12-point bold type. The lien must also tell the owner of the right to contest. Without these statements, the lien is invalid.

Service of the lien

No later than two business days after filing, send a true copy of the lien to the property owner. Use registered or certified mail or statutory overnight delivery. If the owner’s address cannot be found, send it to the contractor as the owner’s agent. For an owner on file with the Secretary of State, the entity address or registered agent address works. If an NOC is filed, also send a copy to the contractor at the NOC address.

Enforcement deadline

Start a lien action within 365 days from the date the lien was filed. Within 30 days after starting the action, file a sworn notice of the action with the superior court clerk in the county where the lien was filed. The lien expires 395 days after filing if no notice of the action is filed.

Owner protections

The total of all liens cannot exceed the contract price of the improvements. An owner can rely on the contractor’s sworn statement that subs and suppliers were paid in a sale, a loan, or final payment, unless a valid preliminary notice or claim of lien was of record at settlement. The owner or contractor can also file a Notice of Contest of Lien and must serve it within 7 days. The claimant then has 60 days from receipt to start the lien action. The lien is extinguished 90 days after the contest is filed if no notice of the lien action is filed.

Georgia quirk: lien waivers

Georgia waivers must substantially follow the statutory forms. A signed waiver binds the claimant to the extent stated. It becomes effective on actual payment, on a separate signed acknowledgment of payment, or 90 days after signing, whichever comes first. If you were not paid, you can keep your rights by filing an Affidavit of Nonpayment in the property’s county within those 90 days.

Where Georgia liens go wrong

  • Missing the Notice to Contractor when a Notice of Commencement is filed.
  • Leaving out the 395-day expiration statement or the right-to-contest notice. Either one invalidates the lien.
  • Signing a statutory waiver before payment and missing the 90-day Affidavit of Nonpayment.
  • Ignoring a Notice of Contest of Lien. The claimant has 60 days from receipt to sue.
Checklist

What do I need to send?

  • Check the superior court records for a Notice of Commencement.
  • If you lack privity with the prime contractor and an NOC is filed, send a Notice to Contractor within 30 days of the NOC or of first delivery, whichever is later.
  • Consider filing an optional Preliminary Notice of Lien Rights within 30 days of first furnishing. Mail a copy within 7 days.
  • File the lien within 90 days of completing your work. Send copies to the owner, and to the contractor if an NOC is filed, within 2 business days.
  • If you signed a waiver and were not paid, file an Affidavit of Nonpayment within 90 days.
  • Know that a Notice of Commencement is due within 15 days after work starts and must be posted on site.
  • Track the Notices to Contractor you receive from lower tiers.
  • File your own lien within 90 days of completing your work and send the owner a copy within 2 business days.
  • Start the lien action within 365 days of filing, then file the notice of the action within 30 days.
  • Get the contractor’s sworn statement that subs and suppliers were paid before final payment, sale, or loan closing.
  • Collect statutory-form lien waivers from each tier.
  • Check the records for preliminary notices and liens before closing or disbursing.
  • A Notice of Contest of Lien, served within 7 days of filing, limits the claimant to 60 days to sue.
Public jobs

Public projects: payment bonds

You can’t lien public property. On state and local jobs, your security is the contractor’s payment bond under the Georgia public works payment bonds: state projects under O.C.G.A. 13-10-60 et seq. and local government projects under O.C.G.A. 36-91-90 et seq..

  • If the contractor complied with the Notice of Commencement rules, a claimant who contracts with a subcontractor (not the contractor) must give the contractor written notice. It is due within 30 days after the NOC is filed or 30 days after first delivery, whichever is later.
  • If the contractor did not comply with the NOC rules, that claimant must give the contractor written notice within 90 days after last furnishing. The notice states the amount claimed and who you furnished to. Send it by registered or certified mail or statutory overnight delivery, or by sheriff service.
  • No bond suit may be brought more than one year after completion of the contract and acceptance of the work by the public authority.
  • Suit is brought in the claimant’s name. The public owner is not made a party.

O.C.G.A. 13-10-63, 13-10-65; 36-91-93, 36-91-95

Payment

Lien waivers

Yes. Georgia has statutory interim and final payment waiver forms. They must substantially follow the statutory language in at least 12-point font. Lien and bond rights cannot be waived before you furnish labor or materials. A waiver becomes effective on the earliest of actual payment, a separate written acknowledgment of payment, or 90 days after signing. To keep rights after signing a waiver without payment, file an Affidavit of Nonpayment in the county where the property is located within those 90 days. A filed affidavit suspends the waiver until payment in full. The 90-day period replaced a 60-day period under SB 315, effective January 1, 2021.

O.C.G.A. 44-14-366

Federal projects

The Miller Act governs federal jobs in every state. Second-tier claimants give written notice to the prime contractor within 90 days after last furnishing; suit within 1 year after last furnishing.

40 U.S.C. 3133

Primary source

Read the Georgia law

We link to the official statute instead of hosting a copy, so you always read the current version. Our summaries were last checked against these sources on October 6, 2026.

Pricing

Georgia services

Flat pricing per document. Premium members pay less on every filing.

Basic: free with signup. Premium: $299 per year.

Basic Membership

Create your free LienNow account to access all our services at standard pricing. No cost, no commitment.  Sign up in minutes and start filing right away at our standard pricing. It’s a good fit for contractors and suppliers who file occasionally.

Premium Membership

Premium includes everything in Basic, plus discounted pricing across our service offerings. If you file notices or liens regularly, the savings can quickly cover the annual fee.

Service Premium Basic
Request for Notice of Commencement Starting at $35 Starting at $60
Notice to Contractor or Preliminary Notice of Lien Rights Starting at $55 Starting at $90
Notice of intent to lien (optional demand) Starting at $75 Starting at $110
Claim of lien: prepare, record and serve Starting at $250 Starting at $425
Lien release / discharge Starting at $110 Starting at $165
Public job bond notice or claim Starting at $210 Starting at $375
Each additional bond notice Starting at $75 Starting at $110
Miller Act bond notice or claim (federal jobs) Starting at $195 Starting at $350
Title search and legal description Starting at $300 Starting at $350
Rush service (within 7 business days) Starting at $75 Starting at $150
Same-day service (24-hour turnaround) Starting at $125 Starting at $200
Electronic recording (e-file) Starting at $45 Starting at $75

Prices are LienNow service fees per document. County recording fees, state registry or portal fees, certified mail, postage and notary fees are billed at cost. Court actions to enforce a lien are handled by an attorney and are not included.

FAQ

Georgia lien questions

How long do I have to file a lien in Georgia?

The claim of lien must be filed within 90 days after you complete your work or furnish your materials. It is filed with the clerk of the superior court in the county where the property is located.

Do I need to send a Notice to Contractor?

Only if a Notice of Commencement is filed and you have no privity of contract with the prime contractor. Then the notice is due within 30 days after the NOC is filed or 30 days after your first delivery, whichever is later.

How long does a Georgia lien last?

You must start a lien action within 365 days from the date the lien was filed and file a notice of that action within 30 days after starting it. The lien expires 395 days after filing if no notice of the action is filed.

I signed a lien waiver but was not paid. What happens?

A statutory waiver becomes effective 90 days after signing unless you file an Affidavit of Nonpayment within that period in the county where the property is located.

Working a Georgia job?

Send us the job. We prepare, serve and record your Georgia notices and liens, and track every deadline.

The information on this page is general information about Georgia law as of the review date shown. It is not legal advice, and LienNow is not a law firm. Deadlines depend on the facts of each project. Consult a licensed Georgia attorney about your specific situation.